Advice · Payments

How much will I pay every month?

Our clients always ask us two things: how much will I pay every month, and how will I know where the budget is? Here’s how it works.

You pay for the work as it’s done

There’s no deposit for the building work. Instead, the work is valued every two or four weeks, depending on the contract you sign, and you pay for the work completed in that period. Each valuation is itemised, so you can see exactly what you’re paying for.

A valuation isn’t a fixed amount. It’s the value of the work actually done, assessed by the project manager and the contract administrator on your project.

Why the valuations go up and down

The valuation won’t be the same every time, and there’s a good reason for it. Some weeks the work moves quickly: the tasks are simpler, there’s less risk, and several trades can work at the same time. Other weeks it slows down, because one task is waiting for another. The foundations can’t be concreted until Building Control has inspected them, plastering waits until the roof and windows keep the weather out, and decorating waits for the plaster to dry.

So if your first valuation is £30,000 and the second is £20,000, don’t worry. That’s normal on a building job, and the next one may well be £30,000 again, or even more than the first.

An example

Here’s how the payments might add up month by month on a £250,000 extension that takes six months on site. You can see the amounts rise and fall with the work.

A £250,000 extension, month by month
Month 1: setting up, demolition, foundations and drains£26,600
Month 2: walls, steels and the roof structure£43,700
Month 3: roof, windows and doors, first fix wiring and plumbing£55,100
Month 4: plastering, floors and second fix£47,500
Month 5: kitchen, bathrooms and tiling£39,900
Month 6: decorating and finishing£24,700
12 months after completion: the 5% held back£12,500
Total£250,000

An example to show how payments follow the work, not a real job. Figures exclude VAT.

We hold back 5% of every payment until the 12-month defects period ends. It gives you security that anything needing attention in that first year gets put right.

How you’ll know where the budget is

Before work starts, we agree the written contract, the programme and the payment schedule, so you know roughly what each month will cost. During the build, a shared online budget shows what has been paid and what is left, including any changes you’ve approved.

Check every valuation, and ask

It’s your money, so it’s a good idea to check every valuation. If anything looks strange, or different from what you were expecting, ask. Trust me, there’s always an explanation.

What else to plan for

  • VAT. Extensions and refurbishments are generally charged at 20%, added to each payment. New-build homes are generally zero-rated.
  • Changes. Anything you add or change is priced for your approval before the work goes ahead, and then appears on the next valuation.
  • Things you buy yourself. If you’re supplying your own kitchen, tiles or bathroom fittings, you pay those suppliers directly, often with a deposit when you order.
  • A contingency. Keep some money aside for changes and anything found once the work starts. Around 10% of the build cost is a sensible starting point.
  • Borrowing. If you’re borrowing, check with your lender how and when they release the money, so it lines up with the payments.

Whoever you choose, be wary of a builder who wants a large payment up front for work that hasn’t started.

Want to know how the payments would work for your project?

Book a site visit. Before any work starts, we’ll agree a payment schedule with you, so you know what’s coming.